ROAD CLOSURES – essential gas works

Reminder: Starting tomorrow, Northern Gas Networks are upgrading the gas infrastructure underneath Middlegate and King Street, resulting in road closures in Penrith town centre.
The works are due to take place in three phases:
Phase 1 – Wednesday 3rd – Friday 26th January 2024 – Closure of Middlegate
Phase 2 – 22nd January – 5th February 2024 – Closure of Devonshire Street
Phase 3 – 5th February – 8th March 2024 – Closure of King Street
All works are to be carried out under Full Road Closures with pedestrian access to be maintained.
Diversion routes for the road closures can be accessed through the Penrith Town Council link below: Diversion maps
All enquiries should be directed to Northern Gas Networks Customer Care on 0800 040 7766