Updates on the Northern Gas Networks upgrading work to the gas infrastructure underneath Middlegate and King Street, resulting road closures in the town centre.
Phase 2 – 22nd January – 5th February 2024 – Closure of Devonshire Street

Phase 3 – 5th February – 8th March 2024 – Closure of King Street

All works are to be carried out under Full Road Closures with pedestrian access to be maintained.
Diversion routes for the road closures can be viewed in the images below.